CIVIL AVIATION AUTHORITY OF THE PHILIPPINES (CAAP)
The CAAP is responsible for implementing policies on civil aviation in order to ensure safe, economical, and efficient air travel. As an independent regulatory body with quasi-judicial and quasi-legislative powers, the CAAP is mandated to set comprehensive, clear and impartial rules and regulations for the Philippine aviation industry.
Night-Rating of Airports
Description: |
To increase the operational efficiency of the country’s airports and reduce daytime flight congestion, the government has night-rated a total of 22 airports nationwide from only 14 night-rated airports. By 2022, the aviation sector is targeting to have 12 more airports night-rated. |
Funding Source: |
GAA |
Start Date: |
2017 |
End Date: |
2022 |
Status: |
22 Commercial Airports Night Rated. By 2022, we will have 12 more commercial airports night-rated. |
Region: |
Nationwide |
Calbayog Airport
Description: |
Improvement of the airport's landside and airside facilities based on the completed FS/Master Plan and in compliance to the CAAP MOSA to enhance safety & efficiency of jet aircraft operations. |
Budget: |
PHP 2.123 Billion |
Funding Source: |
GAA |
Start Date: |
2017 |
End Date: |
Q1 2021 |
Status: |
CY 2016 & CY 2015 - P368.41M CY 2018 - P245.0M |
Region: |
VIII |
Percentage of Completion: |
Substantially completed 98% complete (CY 2016 & CY 2015 - P368.41M) Substantially completed (CY 2018 - P245.0M) |
Catbalogan Airport
Description: |
Improvement and capacity expansion of the existing airport facilities to accommodate turbo propeller aircraft operations. |
Budget: |
PHP 1.120 Billion |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
Q2 2021, Q3 2021 |
Status: |
Ongoing Site Acquisition (MOA with PGU); CY 2018 - P30.0M Construction of Barbed Wire Fence and Runway Strip Grade Correction - Suspended due to ROW issue and presence of rock formation discovered during excavation, which will require adopting a new work station; CY 2019 - P350.0M Removal of Hill Obstruction and Runway Extension |
Region: |
VIII |
Percentage of Completion: |
With 90% work accomplishment (CY 2018 - P30.0M); 69.93% accomplishment (CY 2019 – P350.0M) |
General Santos Airport
Description: |
Rehabilitation/Expansion of Passenger Terminal Building (PTB), Expansion of Apron, Improvement of Air Navigational Facilities and Improvement of Power Supply System & other Landside Facilities to support, promote and sustain Koronadal City's roles as Regional Administrative Center and General Santos City's Role as International gateway and Agri-Industrial, Eco-Tourism Corridor. |
Budget: |
PHP 1.391 Billion |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
Q2 2021 |
Status: |
CY 2015 - P500.00M |
Region: |
XII |
Percentage of Completion: |
Substantially Completed (CY 2015 - P500.00M) |
Davao International Airport
Description: |
Construction of Parallel Taxiway |
Budget: |
PHP 315 Million |
Funding Source: |
GAA |
Start Date: |
2019 |
End Date: |
Q3 2021 |
Status: |
CY 2019 - P315M |
Region: |
XI |
Percentage of Completion: |
22.42% complete (CY 2019 - P315M) |
Dumaguete Airport
Description: |
Asphalt Overlay of Runway; Shoulder grade correction; Rehabilitation of Passenger Terminal Building |
Budget: |
PHP 123.50 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
November 2020 |
Status: |
Completed |
Region: |
VII |
Percentage of Completion: |
Project Completed. |
Antique Airport
Description: |
Upgrading and Capacity Expansion of airport facilities in compliance to CAAP MOSA to support jet aircraft operations and possible resumption of scheduled operations. |
Budget: |
PHP 1.319 Billion |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
Q2 2021, Q3 2021 |
Status: |
CY 2018 - P322.0M CY 2019 - P132.725M Const. of Control Tower, Construction of Elevated Water Tank, Asphalt Overlay of Runway, Strip Grade Correction, and Wind Direction Indicator- ongoing |
Region: |
VI |
Siquijor Airport
Description: |
Improvement of the existing airport facilities based on CAAP MOSA and ICAO standards to enhance safety and efficiency of planned airport operations. |
Budget: |
PHP 40.80 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
October 2020 |
Status: |
Project Completed. |
Region: |
VII |
Percentage of Completion: |
100% completed. |
Cauayan Airport
Description: |
Improvement of airside facilities for night operations of the airport and to support growth of tourism and trade in the area. |
Budget: |
PHP 565 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
Q1 2021 |
Status: |
CY 2019 - P30.50M |
Region: |
II |
Percentage of Completion: |
13.65% complete (CY 2019 - P30.50M) |
San Jose Airport (Mindoro)
Description: |
Continued improvement of the existing airside facilities of the airport to enhance safety of airport operations and support the airline servicing in the area. Compliance with CAAP-MOSA in support of Night Rating. |
Budget: |
PHP 388 Million |
Funding Source: |
GAA |
Region: |
IV-B |
Start Date: |
|
End Date: |
September 2019 |
Status: |
Completed |
Tacloban Airport
Description: |
Continued improvement of airport facilities in compliance to CAAP-MOSA and ICAO. The improvement covers the Construction of New Passenger Terminal Building, Control Tower and improvement of existing landside and terminal facilities. |
Budget: |
PHP 4.776 Billion |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
4Q 2021 |
Status: |
CY 2019 - P50M Construction of Control Tower - ongoing |
Region: |
VIII |
Percentage of Completion: |
68.73% complete (CY 2019 - P50M) |
Zamboanga Airport
Description: |
Development and maintenance of the existing airport up to its optimum capacity. Construction of new airport of international standards. (Runway Taxiway, Apron, Passenger Terminal Building, Cargo Building, Control Tower, Crash Fire Rescue Building, Admin Building, Vehicular Parking Area, Ancillary Buildings and Air Navigational Facilities) to a new site to cater larger jet aircraft. |
Budget: |
PHP 264 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
Q2 2021 |
Status: |
CY 2015 - P42.727M Rehabilitation/Reconfiguration of Terminal Building – ongoing CY 2018 - P221M |
Region: |
IX |
Percentage of Completion: |
95.58% complete (CY 2015 - P42.727M) 50.61% accomplishment (CY 2018 - P221M) |
Dipolog Airport
Description: |
Improvement of Airside facilities for compliance to the CAAP MOSA to support the planned night-time operations |
Budget: |
PHP 336 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
March 2021 |
Status: |
CY 2019 - P52.5M Cont. of Asphalt Overlay of Runway - ongoing |
Region: |
IX |
Percentage of Completion: |
24.79% complete (CY 2019 - P52.5M) |
Ipil Airport
Description: |
Upgrade of runway capacity to enhance safety and efficiency of planned turbo propeller aircraft operations. The airport will provide alternate access to Zamboanga Peninsula and provide air transport services in time of needs and emergency situation in the Zamboanga Region |
Budget: |
PHP 311.60 Million |
Funding Source: |
GAA |
Start Date: |
|
End Date: |
December 2019 |
Status: |
CY 2019 - P30.0M Const. of Fire Station Bldg. - ongoing |
Region: |
IX |
Percentage of Completion: |
12.90% complete (CY 2019 - P30.0M) |