The PPA is the primary government agency concerned with the planning and development of the country's seaports. Established in 1974, the PPA's charter was amended by Executive Order 857, which expanded its functions to include the integration and coordination of ports nationwide.
PPA ON- GOING LOCALLY FUNDED PROJECTS
(as of January 2021)
Rehabilitation and Upgrading of Existing Berth and Back-Up Area Project
Pier 18, Vitas, North Harbor
Description: Rehabilitation and Upgrading of Existing Berth and Back-Up Area and Port Lighting System
Region: NCR
Project Cost: ₱ 298,988,736.73
Funding Source/Year: Corporate Budget
Start Date: 18-Nov-2018
End Date: 01-Jul-2020
Status: Suspended
Percentage of Completion: 37.748%
Construction of Port Operations Building
Port of Currimao, Ilocos Norte
Region: I
Description: Demolition and Removal Works and Port Operations Building
Project Cost: ₱ 112,502,576.39
Funding Source/Year: Corporate Budget
Start Date: 10-Oct-2018
End Date: 09-Aug-2020
Status: On-going Construction
Percentage of Completion: 38.746%
Salomague Port Expansion Project
Port of Salomague, Cabugao, Ilocos Sur
Description: Construction of RC Platform and Construction of RC Pier Extension
Region: I
Project Cost: ₱ 316,087,000.00
Funding Source/Year: Corporate Budget
Start Date: 27-Nov-2019
End Date: 20-Mar-2021
Status: On-going Construction
Percentage of Completion: 93.568%
Capinpin Port Expansion Project
Port of Capinpin, Brgy. Puting Buhangin, Orion, Bataan
Description: Back-Up Area with RoRo Ramp and Platform
Region: III
Project Cost: ₱ 240,098,568.79
Funding Source/Year: Corporate Budget
Start Date: 28-Aug-2019
End Date: 27-Nov-2021
Status: On-going Construction
Percentage of Completion: 76.201%
Construction of Back-Up Area and Port Operations Building
Port of Mauban, Quezon
Description: Construction of Back-Up Area and Widening of Rock Causeway, Construction of Port Operations Building (POB)
Region: IVA
Project Cost: ₱ 135,606,952.10
Funding Source/Year: Corporate Budget
Start Date: 26-Apr-2019
End Date: 18-Jul-2020
Status: On-going Construction
Percentage of Completion: 63.277%
Construction of Back-Up Area and Port Operations Building
Port of Talaga, Mabini, Batangas
Description: Construction of Back-Up Area, Construction of Port Operations Building (POB) and Port Lighting System
Region: IVA
Project Cost: ₱ 67,445,600.00
Funding Source/Year: Corporate Budget
Start Date: 09-Sep-2019
End Date: 27-Apr-2021
Status: On-going Construction
Percentage of Completion: 96.057%
Construction of Back-Up Area and Port Operations Building
Port of Coron, Coron, Palawan
Description: Back-Up Area, RC Wharf With RoRo Ramp and Port Operations Building (POB)
Region: IV-B
Project Cost: ₱ 267,817,495.21
Funding Source/Year: Corporate Budget
Start Date: 07-Jan-2019
End Date: 09-Jun-2021
Status: On-going Construction
Percentage of Completion: 59.385%
Puerto Princesa Port Expansion Project
Port of Puerto Princesa, Palawan
Description: Construction of Back -Up Area
Region: IV-B
Project Cost: ₱ 326,388,788.53
Funding Source/Year: Corporate Budget
Start Date: 19-Dec-2019
End Date: 10-Jun-2021
Status: On-going Construction
Percentage of Completion: 85.210%
Construction of Coastal Access Road
Port of Calapan, Calapan City, Oriental Mindo
Description: Construction of Coastal Access Road and Port Lighting System
Region: IV-B
Project Cost: ₱ 140,810,163.43
Funding Source/Year: Corporate Budget
Start Date: 08-Apr-2019
End Date: 30-Jun-2020
Status: On-going Construction
Percentage of Completion: 99.453%
Balanacan Port Expansion Project
Port of Balanacan, Marinduque
Description: Demolition and Removal Works, Back-Up Area, RC Wharf and RoRo Ramp
Region: IV-B
Project Cost: ₱ 113,999,203.94
Funding Source/Year: Corporate Budget
Start Date: 05-Dec-2019
End Date: 27-Jan-2021
Status: Suspended
Percentage of Completion: 0.000%
Tablas (Poctoy) Port Expansion Project
Port of Tablas(Poctoy), Odiongan, Romblon
Description: Demolition and Removal Works, RC Pier Rehabilitation and Extension and Construction of Back-Up Area
Region: IV-B
Project Cost: ₱ 147,488,603.62
Funding Source/Year: Corporate Budget
Start Date: 18-Feb-2020
End Date: 12-May-2021
Status: On-going Construction
Percentage of Completion: 45.518%
Rehabilitation/ Upgrading of Damaged Wharf Project
Port of Legazpi, Base Port, Legazpi City, Albay
Description: Rehabilitation/Upgrading of RC Wharf and Pavement
Region: V
Project Cost: ₱ 154,701,297.82
Funding Source/Year: Corporate Budget
Start Date: 24-Aug-2015
End Date: 10-Sep-2017
Status: On-going Construction
Percentage of Completion: 98.165%
Rehabilitation/ Upgrading of Damaged Wharf Project
Port of Tabaco, Tabaco City, Albay
Description: Rehabilitation/Upgrading of RC Wharf and Pavement
Region: V
Project Cost: ₱ 192,588,909.00
Funding Source/Year: Corporate Budget
Start Date: 31-Jul-2015
End Date: 27-May-2017
Status: On-going Construction
Percentage of Completion: 98.469%
Extension of RC Pier and Provision of RoRo Ramp
Port of Virac, Catanduanes
Description: RC Pier and RoRo Ramp, Mooring and Fendering
Region: V
Project Cost: ₱ 50,474,887.98
Funding Source/Year: Corporate Budget
Start Date: 08-Oct-2018
End Date: 23-Mar-2020
Status: On-going Construction
Percentage of Completion: 73.708%
Cobo Port Development Project
Port of Cobo, Pandan, Catanduanes
Description: Construction of Rock Causeway and Back-Up Area
Region: V
Project Cost: ₱ 49,410,742.00
Funding Source/Year: Corporate Budget
Start Date: 23-Sep-2019
End Date: 18-Jul-2020
Status: On-going Construction
Percentage of Completion: 0.906%
Construction of Back-Up Area
Port of Esperanza, Masb
Description: Construction of Back-Up Area and Port Lighting System
Region: V
Project Cost: ₱ 140,195,806.36
Funding Source/Year: Corporate Budget
Start Date: 30-May-2019
End Date: 22-Jul-2020
Status: On-going Construction
Percentage of Completion: 48.918%
Construction of Port Operations Building (POB) and Transit Shed
Port of Masbate, Masbate City
Description: Removal Works, Port Operations Building and Transit Shed
Region: V
Project Cost: ₱ 142,029,130.56
Funding Source/Year: Corporate Budget
Start Date: 12-Feb-2020
End Date: 18-Sep-2021
Status: On-going Construction
Percentage of Completion: 30.150%
Cawayan Port Improvement Project
Port of Cawayan, Masbate
Description: Demolition and Removal Works, Back-Up Area and Causeway, Port Operations Building, Pumphouse and Guardhouse
Region: V
Project Cost: ₱ 146,998,000.58
Funding Source/Year: Corporate Budget
Start Date: 01-Jul-2020
End Date: 23-Sep-2021
Status: On-going Construction
Percentage of Completion: 0.603%
Construction of RoRo Ramp, Platform, and Pier Extension
Port of Bulan, Bulan, Sorsogon
Description: Construction of RC Platform, RoRo Ramp and RC Pier
Region: V
Project Cost: ₱ 119,717,992.43
Funding Source/Year: Corporate Budget
Start Date: 06-Feb-2020
End Date: 11-Sep-2021
Status: On-going Construction
Percentage of Completion: 59.372%
Matnog Port Expansion
Port of Matnog, Matnog, Sorsogon
Description: Construction of Back-Up Area, Upgrading of RC Platform and Trestle, Construction of Back-Up Area Platform, Two (2) RoRo Ramp and Paving of Existing Back-Up Area and Port Lighting System
Region: V
Project Cost: ₱ 323,627,472.75
Funding Source/Year: Corporate Budget
Start Date: 09-Dec-2015
End Date: 29-Sep-2018
Status: On-going Construction
Percentage of Completion: 83.551%
Construction of Back-Up Area Port of Dumangas, Iloilo
Port of Dumangas, Dumangas, Iloilo
Description: Construction of Back-Up Area and Port Lighting System
Region: VI
Project Cost: ₱ 237,931,283.84
Funding Source/Year: Corporate Budget
Start Date: 04-Jun-2019
End Date: 02-Sep-2021
Status: On-going Construction
Percentage of Completion: 73.554%
Basiao Port Development Project
Port of Basiao, Ivasan, Capiz
Description: Back-Up Area and Causeway, Roro Ramp
Region: VI
Project Cost: ₱ 60,400,000.00
Funding Source/Year: Corporate Budget
Start Date: 08-Jun-2020
End Date: 03-Apr-2021
Status: On-going Construction
Percentage of Completion: 74.739%
Banago Port Expansion Project
Port of Banago, Bacolod City, Negros Occidental
Description: Construction of Back-Up Area with RoRo Ramp on Piles, Widening of Access Road on Piles and Port Lighting System
Region: VI
Project Cost: ₱ 362,698,606.45
Funding Source/Year: Corporate Budget
Start Date: 08-Jan-2019
End Date: 17-Nov-2020
Status: On-going Construction
Percentage of Completion: 88.988%
Manoc Manoc Cargo Port Project
Port of Manoc Manoc, Malay, Aklan
Description: Construction of Back-Up Area, Construction of Access Road and Port Lighting System
Region: VI
Project Cost: ₱ 132,828,205.91
Funding Source/Year: Corporate Budget
Start Date: 30-Aug-2019
End Date: 22-Oct-2020
Status: Suspended
Percentage of Completion: 20.348%
Alegria Port Development Project
Port of Alegria, Buruanga, Aklan
Description: Construction of Back-Up Area, RC Platform 1, RC Platform 2, RC Pier, RoRo Ramp 2 Units, Breasting Dolphin and Port Lighting System
Region: VI
Project Cost: ₱ 214,850,000.00
Funding Source/Year: Corporate Budget
Start Date: 30-Aug-2019
End Date: 22-Oct-2020
Status: On-going Construction
Percentage of Completion: 4.595%
Maribojoc Port Improvement Project
Port of Maribojoc, Maribojoc, Bohol
Description: Improvement of Existing Rock Causeway, Construction of Back-Up Area with RoRo Ramp on Fill, Construction of Breasting Dolphin and Port Lighting System
Region: VII
Project Cost: ₱ 480,948,770.01
Funding Source/Year: Corporate Budget
Start Date: 12-Mar-2018
End Date: 18-Feb-2021
Status: On-going Construction
Percentage of Completion: 89.320%
Construction of Additional Fastcraft Berth
Port of Tagbilaran, Tagbilaran City, Bohol
Description: Fastcraft Berth and Covered Walkway
Region: VII
Project Cost: ₱ 88,032,936.61
Funding Source/Year: Corporate Budget
Start Date: 26-Feb-2020
End Date: 11-Nov-2020
Status: On-going Construction
Percentage of Completion: 79.345%
Construction of Back-Up Area Port of Jetafe, Bohol
Port of Jetafe, Bohol
Description: Back-Up Area
Region: VII
Project Cost: ₱ 163,296,490.50
Funding Source/Year: Corporate Budget
Start Date: 09-Mar-2020
End Date: 03-Mar-2021
Status: On-going Construction
Percentage of Completion: 35.024%
Construction of Back-up Area with Continuous RoRo Ramp & Port Operations Building
Port of Tubigon, Bohol
Description: Back-Up Area with Continuous RoRo Ramp on Fill and Port Operations Building
Region: VII
Project Cost: ₱ 445,388,282.65
Funding Source/Year: Corporate Budget
Start Date: 16-Mar-2020
End Date: 09-May-2021
Status: On-going Construction
Percentage of Completion: 38.984%
Siquijor Port Expansion Project
Port of Siquijor, Negros Oriental
Description: Construction of RC Wharf with RoRo Ramp, Back-Up Area and Port Lighting System
Region: VII
Project Cost: ₱ 160,092,960.79
Funding Source/Year: Corporate Budget
Start Date: 10-Dec-2018
End Date: 26-Sep-2020
Status: On-going Construction
Percentage of Completion: 98.596%
Rehabilitation of Existing R.C. Pier
Port of Baybay, Leyte
Description: Demolition, Removal and Excavation Works, Transition Ramp and Extension of RoRo Ramp on Fill and Rehabilitation of Existing RC Pier
Region: VIII
Project Cost: ₱ 120,851,884.27
Funding Source/Year: Corporate Budget
Start Date: 08-Jan-2020
End Date: 02-Mar-2021
Status: On-going Construction
Percentage of Completion: 96.156%
Palompon Port Improvement Project
Port of Palompon, Leyte
Description: Demolition and Removal Works, Construction of Back-Up Area with RoRo Ramp on Fill, Construction of Port Operations Building and Construction of Transit Shed
Region: VIII
Project Cost: ₱ 122,188,000.00
Funding Source/Year: Corporate Budget
Start Date: 20-Aug-2018
End Date: 31-Oct-2020
Status: On-going Construction
Percentage of Completion: 73.136%
Extension of RC Wharf
Port of Guiuan, Leyte
Description: Extension of RC Wharf, Mooring Fendering System
Region: VIII
Project Cost: ₱ 23,871,127.50
Funding Source/Year: Corporate Budget
Start Date: 20-Nov-2017
End Date: 15-Aug-2019
Status: On-going Construction
Percentage of Completion: 69.347%
Construction of Port Operations Building (POB) and RoRo Ramp
Port of Maasin, Southern Leyte
Description: Demolition and Removal Works, Construction of Port Operations Building (POB) and Construction of RoRo Ramp
Region: VIII
Project Cost: ₱ 48,287,883.74
Funding Source/Year: Corporate Budget
Start Date: 02-May-2019
End Date: 24-Jun-2020
Status: On-going Construction
Percentage of Completion: 29.689%
Dapitan Port Development Project
Port of Dapitan, Dapitan City, Zamboanga del Norte
Description: Construction of Back-Up Area, Lighting System
Region: IX
Project Cost: ₱ 322,867,907.64
Funding Source/Year: Corporate Budget
Start Date: 09-Mar-2017
End Date: 12-Apr-2020
Status: On-going Construction
Percentage of Completion: 92.923%
Construction of RC Pier Extension
Port of Dapitan, Dapitan City, Zamboanga del Norte
Description: Construction of RC Pier Extension
Region: IX
Project Cost: ₱ 68,774,429.35
Funding Source/Year: Corporate Budget
Start Date: 12-Sep-2018
End Date: 11-Jul-2021
Status: On-going Construction
Percentage of Completion: 68.483%
Isabela Port Improvement Project
Port of Isabela, Isabela City, Basilan
Description: Improvement of Existing RC Wharf, Construction of RoRo Ramp and RC Platform, Port Lighting System
Region: IX
Project Cost: ₱ 361,068,041.92
Funding Source/Year: Corporate Budget
Start Date: 25-Jan-2018
End Date: 14-Dec-2020
Status: On-going Construction
Percentage of Completion: 40.017%
Ozamiz Port Improvement Project
Port of Ozamiz, Ozamiz City, Misamis Occidental
Description: Construction of RC Pier, Construction of Back-Up Area, Paving of Existing Back-Up Area and Port Lighting System
Region: X
Project Cost: ₱ 177,954,409.04
Funding Source/Year: Corporate Budget
Start Date: 23-Mar-2018
End Date: 24-Jan-2020
Status: On-going Construction
Percentage of Completion: 97.074%
Construction of Back-Up Area and RC Wharf on Fill
Port of Ozamiz, Ozamiz City, Misamis Occidental
Description: Construction of Back-Up Area, Construction of Breasting Dolphin and Port Lighting System
Region: X
Project Cost: ₱ 324,872,239.42
Funding Source/Year: Corporate Budget
Start Date: 20-Sep-2019
End Date: 11-May-2021
Status: On-going Construction
Percentage of Completion: 47.342%
Extension of RC Pier and Construction of Back-Up Area with RoRo Ramp-on-Fill
Port of Sultan Naga Dimaporo, Lanao del Norte
Description: Construction of RC Pier, Construction of Back-Up Area, Upgrading of Existing Rock Causeway, Extension of Rock Causeway and Port Lighting System
Region: X
Project Cost: ₱ 240,301,400.87
Funding Source/Year: Corporate Budget
Start Date: 26-Mar-2019
End Date: 17-Jul-2020
Status: On-going Construction
Percentage of Completion: 81.345%
Extension of RC Wharf and Reclamation of Back-Up Area
Port of Iligan, Iligan City, Lanao del Norte
Description: Construction of Back-Up Area, Construction of RC Wharf and Port Lighting System
Region: X
Project Cost: ₱ 296,289,853.15
Funding Source/Year: Corporate Budget
Start Date: 18-Feb-2020
End Date: 21-Jun-2022
Status: On-going Construction
Percentage of Completion: 37.106%
Upgrading of General Cargo Berth
Port of Davao, Sasa, Davao City
Description: Upgrading of General Cargo Berth and Port Lighting System
Region: XI
Project Cost: ₱ 883,490,000.00
Funding Source/Year: Corporate Budget
Start Date: 30-May-2019
End Date: 13-Mar-2022
Status: On-going Construction
Percentage of Completion: 45.674%
Construction of Cruise Ship Port
Port of Jubang, Dapa, Surigao del Norte
Description: Construction of RC Wharf, RC Platform, Back-Up Area, Access Road with Back-Up Area and Port Lighting System
Region: XIII
Project Cost: ₱ 598,128,007.75
Funding Source/Year: Corporate Budget
Start Date: 12-Nov-2018
End Date: 13-Feb-2021
Status: On-going Construction
Percentage of Completion: 57.152%
Port of Jubang, Dapa Surigao del Norte
Port of Jubang, Dapa, Surigao del Norte
Description: Construction of RC Wharf, RC Platform, Back-Up Area, Access Road with Back-Up Area and Port Lighting System
Region: XIII
Project Cost: ₱ 636,800,105.00
Funding Source/Year: Corporate Budget
Start Date: 12-Nov-2018
End Date: 10-May-2021
Status: On-going Construction
Percentage of Completion: 48.999%
Doña Helene Port Expansion Project
Port of Doña Helene, Socorro, Surigao del Norte
Description: Upgrading of Existing Back-Up Area and Rock Causeway, Construction of Back-Up Area, Construction of RC Platform and RoRo Ramp Construction of Breasting Dolphin and Port Lighting System
Region: XIII
Project Cost: ₱ 63,412,200.00
Funding Source/Year: Corporate Budget
Start Date: 24-Oct-2019
End Date: 17-Oct-2020
Status: On-going Construction
Percentage of Completion: 50.051%
Expansion of Back-Up Area with RoRo Ramp
Port of Lipata, Surigao City, Surigao del Norte
Description: Construction of Back-Up Area, Construction of RC Wharf With RoRo Ramps and Port Lighting System
Region: XIII
Project Cost: ₱ 253,030,720.00
Funding Source/Year: Corporate Budget
Start Date: 02-Mar-2020
End Date: 13-May-2022
Status: On-going Construction
Percentage of Completion: 55.605%